Construction project to update the library bathrooms and drinking fountain
The update of the library’s bathrooms and replacement of the drinking fountain is starting on Monday, March 10.
Closed Monday, March 10
This will be the ‘demo day’, so the library will be closed. The library will reopen on Tuesday, March 11 at 10am.
Library hours during construction?
The library will remain open during the majority of this project, despite some noise and dust. However, we may need to close while major parts of the project, like installing the drinking fountain, are happening. We will announce any necessary closures as soon as they are scheduled
How long will this project last?
This project will last approximately one month.
What is the scope of the project?
All three bathrooms will get fresh wall finishes, flooring, fixtures and lighting. We will also add a changing table in the lower level bathroom. The drinking fountain will be replaced with a new model which includes a water bottle filler.
Project cost?
This update to the library building will cost approximately $43,500. Easling Construction is the contractor for this project.